Insights · Guide
Before You Build
A plain-language guide to working with an architect, from your first idea to the day construction finishes.
Most building problems start long before construction, with an unclear brief, a budget nobody tested or drawings that contractors read differently. A good design process prevents them. This guide explains how that process works, what you should prepare, and what you will decide at each step.
1. Prepare these before your first meeting
You don't need drawings to start. You need clear answers to a few questions, because every design decision builds on them.
- Your construction budget. Give a realistic figure for the building itself. It shapes size, structure and materials more than anything else.
- The type of building. For example, a private house, villas for rent, a hotel or a commercial building.
- How it will be used. Who uses which spaces, when, and how the inside and outside connect.
- Your land. The title deed, plot size, a survey if you have one, and photos of the site and its access road.
- Who it is for. For a project you will sell or rent, describe the target buyers or guests: age group, lifestyle and occupation.
2. The six stages of a project
Design moves from big decisions to small ones. Each stage ends with a review and your written approval before the next one begins. This protects you: you never pay for detailed work on an idea you haven't agreed to.
Pre-Design
15 daysThe architect listens first. Together you pin down your budget, the type of building, how it will be used and who it is for. The architect then presents three different concept directions so you can choose a path before any drawing begins.
- You decide
- Which concept direction to develop
- You receive
- Concept booklet and detailed concept booklet
Schematic Design
45 daysThe chosen concept becomes a real layout, developed in three rounds of about 15 days, with your review after each round. The site and the planning rules are analysed, massing options are modelled in 3D, and engineers set the direction for structure, air-conditioning and electrical systems.
- You decide
- Layout, building shape and area mix
- You receive
- Site analysis, master plan, floor plans, 3D views, area list, first cost estimate
Design Development
30 daysThe approved layout is refined in detail and coordinated with the structural, mechanical and electrical engineers. This is where materials are chosen: floors, walls, ceilings, sanitaryware, lighting, doors and windows.
- You decide
- Materials and the look of the building
- You receive
- Detailed plans, elevations, sections, general specification
Construction Drawings
60 daysThe complete drawing set is produced: architecture plus structural, mechanical, electrical and sanitary engineering. These drawings are what you submit to the authorities to apply for a building permit.
- You decide
- Final design for permit submission
- You receive
- Permit drawings for every discipline
Bidding
60 daysThe permit drawings become a tender package so contractors can price exactly the same scope. It includes a detailed construction cost, a material specification and a blank bill of quantities (BOQ) for each bidder to fill in.
- You decide
- Which contractor to appoint
- You receive
- Bidding drawings, detailed cost, specification, blank BOQ
Construction Support
Length of buildContract drawings are prepared for your agreement with the contractor. During construction the architect inspects the work, reviews the contractor's shop drawings, reports progress and certifies work completed.
- You decide
- Questions and changes on site
- You receive
- Contract drawings, BOQ, specification, progress reports
3. The rules that shape your design
Two things limit what can be built on any plot: the site itself and the law. A professional analyses both early in Schematic Design, so the design you fall in love with is one you can actually build.
The site
- Orientation, sun and wind
- Topography and slope
- Climate and environment
- Access, traffic and pollution
- Existing trees and structures
- Views, neighbours and nearby landmarks
- Energy use
Planning law and building code
- Planning zone of the plot
- Floor Area Ratio (FAR): total floor area allowed
- Open Space Ratio (OSR) and building coverage
- Required green area
- Maximum building height
- Minimum setback distances
- Slope limits for construction
4. What is included, and what is extra
A standard architectural service covers architecture plus the core engineering: structure, mechanical (air-conditioning and ventilation), electrical, and sanitary systems. Some projects need more. These services are usually agreed and priced separately, so ask about them at the start.
| Optional service | When you may need it |
|---|---|
| Civil engineering | Site roads, drainage and utilities, especially on large or sloping plots |
| Landscape design | Gardens, pools and outdoor spaces designed to fit the building |
| Interior design | Fitted interiors, furniture and finishes beyond the general specification |
| Tender management and bid evaluation | Inviting contractors, issuing documents and comparing prices on your behalf |
| Construction contract drafting | Preparing the agreement between you and the contractor |
| Detailed cost accounting | Tracking construction spending in detail during the build |
5. How fees usually work
Professional fees are normally agreed as one total, then paid in instalments. Each instalment falls due when a stage, or a round within it, is delivered and approved. The largest share usually falls on the construction drawings, the most labour-intensive stage. Ask for the payment schedule in writing, and check that every instalment is tied to a clear deliverable.
6. Why the bidding stage matters
When contractors price from rough drawings, each one assumes something different. Their prices can't be compared, and the gaps often come back later as extra charges. A proper tender package fixes this. Every bidder prices the same drawings and specification, on the same blank bill of quantities, so you can compare offers line by line.